Project Description:

The Iron removal plant has been designed to produce 10 000 cubic meter of potable water per day using Sardasht water which was pumped to Kharg Island through corroded old steel :pipeline The water was polluted with heavy amount of Iron The plant consists of the following process units

  • Feed pipe line
  • Aerators
  • Clarifiers
  • Sand Filters
  • Dual Media Filters
  • Activated Carbon Filters
  • Back Wash Basin
  • Chlorination Package

Scope of Work:

  • Complete Basic and Detail Engineering Design
  • Procurement and Supply of Equipment
  • Civil Construction
  • Mechanical Installation and Erection
  • Electrical and Instrumental Installation
  • Pre commissioning
  • Commissioning
  • Start up
  • Technical Assistance Services

Image Gallery