Project Description

This project has been defined as a continuation, revision, and update of the previous project documentation It includes a comprehensive review and updating of the documents related to the .ignition system, as well as the control and monitoring of Flares and Heaters, incorporating newly added sites and flares

:Theplants and relevant revamping systems are located in Kohkilooyeh Boyer Ahmad, Khuzestan and Booshehr provinces and are including

  • Gachsaran LP I Gas Station (Flare).
  • Gachsaran LP II Gas Station (Flare).
  • Gachsaran LP III Gas Station (Flare).
  • Gachsaran LP IV Gas Station (Flare).
  • Gachsaran HP Gas Station (Flare).
  • Siahmakan HP Gas Station (Flare).
  • Gachsaran II Desalting Plant (Flare).
  • Gachsaran IV Oil Station (Flare).
  • Ragsefid II Gas and Oil Stations (Flare).
  • Ragsefid II Desalting Plant ( Flare,Oil Heater).
  • (Bibihakimeh I Gas Station (Flare.
  • (Bibihakimeh II Gas and Oil Stations (Flare.
  • (Bibihakimeh I Oil Station (Flare.
  • Bibihakimeh II Desalting Plant (Oil Heater).
  • (NGL 900 Plant (Oil Heater,Flare.
  • Pazanan II Desalting Plant ( Oil ,Flare,Heater).
  • (Pazanan II Oil Station(Flare.
  • (Binak Gas Station (Flare.
  • (Binak Desalting Plant ( Heater Flare.
  • (Nargesi Oil Station (Flare.
  • (Nargesi Gas Station (Flare.
  • (NGL 1200 Plant (Flare.
  • (NGL 1300 Plant (Flare.

Scope of Work:

  • Site Visit, Data Gathering and Preparation of Complete Site Statuses and DTS Reports.
  • Comparison of all Existing Ignition Systems and Preparation of Relevant Reports to Choose the Best System.
  • Complete Conceptual, Basic and Detail Engineering Design.
  • Preparation of Material Take off (MTO) for All New/Relocated Items.
  • MR Preparation.
  • Economical Studies and Price Evaluation for PC Contract.
  • Preparation of Scope of Work and Tender Documents for PC Contract.