Project Description

This project is consisting of 3 parts including Desalting, Flare Managing and Connection Line Design

Desalting

As the salinity of plant s feed (receiving from Tabnak Vavary and Shanul gas fields) is gradually increasing The scope of this part of project is designing a desalter package for each of No 400 No 500 and No 103 units Desalter package will be located after the stabilizer in each unit The design target is to decrease the salinity to the acceptable range based on IOM regulations and international standards

Flare Managing

The scope of this part is to review and redesign of the complete flare system in

units 400 500 140 and finding solution for defined items, mainly including

Review of existing flares and finding the best solution for decreasing the required purge gas.

Redesign of flaring network and flare headers based on HP/LP detachment concept

Complete revamping of flares ignition system and pilots

Connecting the cold vent of compressor station to existing flare system

Connection Line

This part includes design of a connecting line for connecting unit 100 (in parsian - IPlant) to the existing connection line between units 400 and 500 (in parsian ه=Plant) considering all process and control requirements and routing limitations.

Scope of Work:

Feasibility Study of the project based on the existing plants process

information and find out the optimum process design in each part

Preparation and delivery of the basic engineering package in each part

Performing detail engineering and preparation of tender documents for

construction and installation works at site in each part